Red states relocate to quit transmission lines that would offer relief to Minnesota ratepayers

Debt: Pixabay

by Brian Martucci, Minnesota Reformer

As Washington Republicans’ strikes on renewable energy and voracious data center electricity need threaten to press electrical energy rates higher , utility compensations in five red states are combating a widely-supported effort to maintain power expenses in check.

They have actually submitted a issue asking federal power regulators to stop growth of a $ 22 billion slate of suggested high-voltage electrical transmission lines that would expand an existing network extending from Kentucky to Minnesota and the Dakotas. They argue the Upper Midwest’s major power grid operator drastically overemphasized the lines’ monetary and environmental merits while improperly allocating their building and construction expenses to states that say they don’t require them.

On the other side is a motley coalition of electrical utilities, tech companies, agribusinesses, ecological teams, a Republican guv and a pair prospective 2028 Democratic presidential competitors that sustain the financial investment.

The brand-new lines are anticipated to be in service by 2034, enhancing links between the gusty, warm Plains states and population facilities additionally southern and east.

The contest the transmission lines highlights a key flashpoint in the energy sphere, as more affordable renewable resource runs headlong into an absence of transmission capacity and political hostility from Republican states.

“These enhancements will certainly save consumers billions by avoiding costly inefficiencies and branching out the marketplace of generation resources throughout the region,” Gov. Tim Walz, that’s running for a 3rd term, stated in a Sept. 16 letter to the Federal Power Regulatory Payment.

Michigan Gov. Gretchen Whitmer and Illinois Gov. J.B. Pritzker made similar debates in letters earlier this month. Like Minnesota, Michigan and Illinois have statutory requireds for 100 % carbon-free electrical energy– Michigan by 2040 and Illinois by 2050 Both guvs are potential 2028 presidential prospects.

Gov. Kim Reynolds of wind-rich and mandate-free Iowa additionally pressed back on the five energy commissions’ problem in a Sept. 5 letter hailing her state’s” all-of-the-above energy method” and name-checking President Trump.


The Northeast encounters distinct obstacles, including transportation electrification, maturing framework, renewable assimilation, grid innovation, and progressively severe climate. DTECH ® Northeast will certainly put together leading stakeholders to take on these issues head-on, providing understandings right into innovative technologies and techniques that ensure dependability, sustainability, and consumer satisfaction. Join us in Boston, Massachusetts, from November 17 – 19, 2025


The new facilities “will certainly make sure ongoing dependability and resilience of the electric grid not just in Iowa but also throughout the area,” she created. Eliminating the brand-new transmission financial investments, she included, can in turn stall 7 atomic power plants’ worth of brand-new nuclear power plant in her state “by months to even years.”

The Indiana-based nonprofit that runs the electric grid in Minnesota and parts or every one of 14 various other states insists the proposed lines– collectively referred to as LRTP Tranche 2 1– might pay for themselves more than 3 times over

That’s sufficient to qualify them as “multi-value tasks” whose costs can be spread out generally across the territory of the Midcontinent Independent System Operator– called MISO– including among ratepayers in Republican-controlled states without ambitious decarbonization goals. Stakeholders across the region had ample chance to consider in on the suggested lines, a MISO spokesperson told the Agitator

Prior to wrapping up the tranche last year, MISO led “a collaborative procedure that consisted of significant stakeholder interaction along with greater than 300 meetings and feedback on the solutions and benefits,” MISO spokesman Brandon Morris said in an email.

Representing the public utility payments of Montana, North Dakota, Mississippi, Louisiana and Arkansas, the plaintiffs said that the price allocation effectively funds the development of wind and solar farms far from populace centers– and, by extension, Midwestern blue states’ tidy energy objectives. As opposed to asking Montana and North Dakota to share the concern, they stated states like Minnesota, Michigan and Illinois need to build more tidy energy and transmission within their own boundaries.

North Dakota’s GOP congressional delegation stated much the same in a Sept. 11 letter prompting regulators to provide the problem and reverse the cost allowance framework.

“The present technique to cost allocation is an aid plan that relieves particular states of the costs of their most aggressive energy plans … while out-of-state ratepayers pay,” U.S. Rep. Julie Fedorchak and Sens. Kevin Cramer and John Hoeven composed.

Belying the complaint, Minnesota is developing plenty of tidy power on home soil. Renewables supplied 33 % of the state’s electrical energy in 2024, according to Clean Energy Economic Situation Minnesota , and a state law that speeds up allowing for wind, solar and various other energy facilities took effect in July. Solar energy jobs approved by the Minnesota Public Utilities Compensation since then will certainly supply almost a nuclear reactor’s worth of energy as they come online over the following few years.

But regardless of how it’s created, experts state high-voltage transmission is needed to move electrical energy throughout longer ranges.

“One of the crucial principles of a renewables-based system is you desire the grid to be larger than the climate,” said Mike Schowalter of Fresh Power, a St. Paul-based clean energy not-for-profit.

Transmission lines constructed to provide coal-fired power from North Dakota to Minnesota now catch a reasonable amount of wind, which supplies more than one-third of North Dakota’s electricity. North Dakota officials said throughout MISO’s stakeholder engagement procedure– before the utility commissioners’ July grievance– that they would love to see more of that, Schowalter said.

East of the Rockies, power usually relocates from west to east, but the prevailing circulation typically turns around throughout winter storms and various other extreme climate events, Schowalter described. To guarantee everyone has adequate power under the circumstances, utilities can either develop lots of transmission and some power plants or lots of power plants and some transmission.

“The last is far more pricey,” Schowalter claimed.

Building great deals of brand-new gas-fired power plants– something that’s already likely to take place as more AI information centers come online– could push up gas costs, Schowalter said. Because gas plants often establish the neighborhood price of electrical power , and fuel represents a significant portion of their operating expenses, that implies more expensive power.

“The globe that the plaintiffs imagine is just one of much more pricey electrical power, and our AI market is mosting likely to be at danger,” he stated. “We are shooting ourselves in the foot.”

MISO appears to concur.

“The complaint threatens the capacity of MISO and its state partners to sustain the expected development in power need and would certainly increase expenses to clients within the MISO area by replacing an effective, regional option with a piecemeal one,” the grid operator stated in a Sept. 9 submitting that called the utility commissioners’proposal “slipshod and unrealistic.”

Schowalter said a problem for Tranche 2 1 would certainly tinker the fragile grid preparation procedure and postpone the arrival of brand-new nuclear power plant that MISO, utilities and huge consumers were trusting.

Actually, those delays might slow deployment of the the very gas plants indicated to support the grid as AI data centers increase.

The Information Center Union, a tech sector profession group, made this factor in a Sept.9 filing.

Though Schowalter claimed MISO designated much less than 2 % of complete Tranche 2 1 costs to North Dakota and Montana, their utility commissions’ problems make sense: They do not intend to pay at all for financial investments they believe benefit others.

The other 3 compensations’ motivations are less apparent since government energy regulators have actually prevented MISO from alloting Tranche 2 1 prices across its southern area.

Colby Cook of the Louisiana Civil service Compensation informed the Reformer that LPSC “has actually constantly sustained the MISO local transmission planning procedures” however signed up with the grievance for two main reasons.

The very first was “the unreasonable underlying presumptions relied upon to justify these projects as (multi-value jobs),” Chef stated in an e-mail. Beyond decarbonization benefits, the problem challenged MISO’s quotes of just how cost-effectively the new high-voltage lines can be built and the level to which they would enhance grid dependability and decrease the demand for new nuclear power plant.

Secondly was the problem that Louisiana– though not currently needed to pay the proposed new prices– could be responsible later on.

Legal reps for the other four commissions did not reply to a Reformer ask for remark.

Maybe identifying the demand for a fast resolution, the complainants themselves have actually asked government regulators to expedite the complaint. It’s unclear whether the feds will concur.

In the meanwhile, a vital piece of the Midwest’s future power grid is in limbo.

“If the plaintiffs achieve success, MISO would certainly have to redesign a minimum of a year’s worth of job,” Schowalter stated.

Minnesota Agitator belongs to States Newsroom, a nonprofit information network sustained by grants and a union of contributors as a 501 c( 3 public charity. Minnesota Radical keeps editorial freedom. Contact Editor J. Patrick Coolican for questions: [email protected]

Leave a Reply